A read-only slash command that estimates effort for a task by grounding it in the actual codebase: it pins down scope and explicit non-scope, decomposes the work into independently-shippable subtasks, sizes each as a T-shirt with a rough range, sums to a total, then surfaces the risks, unknowns, dependencies, and assumptions that move the number — plus the first slice to ship to de-risk it.

Estimate the effort to do the task in $ARGUMENTS by grounding it in the real codebase, not in vibes. This is an analysis pass only — read to understand, then deliver an estimate. Do not edit, run, or create anything.

Scope

Treat $ARGUMENTS as the task to size — a feature, a refactor, a migration, a bug ("add SSO via SAML", "split the monolith's billing module into a service", "fix the flaky checkout test"). If it names files, symbols, or routes, those are where your investigation starts.

If $ARGUMENTS is empty, do not invent a task. Ask one question — "What task should I estimate?" — and stop until they answer.

WARNING

Read-only mode. Your only output is the written estimate. An estimate is a range under stated assumptions, never a commitment or a deadline — say so explicitly in the report so nobody quotes the midpoint as a promise.

Step 1 — Pin down scope and non-scope

Restate the task in one sentence. Then list what is explicitly out of scope — the adjacent work a reader might assume is included but isn't (migrations of old data, the admin UI, rollback tooling, docs). Unbounded scope is the single biggest source of estimate error; naming the boundary is half the job.

If the task hides a fork that changes the size by an order of magnitude (rewrite vs. patch? backward-compatible vs. breaking? one provider vs. a pluggable abstraction?), surface it as an open question — do not silently pick the cheap reading.

Step 2 — Explore the code to ground the estimate

Read enough of the repo to size against reality. Do not guess the structure — find it.

# Find the symbols, routes, or modules the task touches
grep -rn "checkoutHandler" src/
 
# Map the surrounding structure and blast radius
find src -path '*billing*' -name '*.ts'
 
# Gauge how much code already exists vs. needs writing
grep -rln "PaymentProvider" src/

Open the entry points, trace one level of callers and callees, and note the seams the change crosses: shared types, config, public APIs, tests, and anything with many inbound references. A change behind a clean interface is small; one that ripples through dozens of call sites is not.

NOTE

Existing tests are an effort multiplier in both directions. Good coverage on the touched area shrinks the estimate (you can refactor safely); zero coverage on a critical path inflates it (you must write characterization tests before you dare touch it). Check before you size.

Step 3 — Decompose into independently-shippable subtasks

Cut the work into subtasks that each land on their own and deliver a checkable result — schema, then store, then the wiring, then tests, then docs. Estimating the whole as one lump is where guesses hide; estimating parts forces you to confront each one. Anything you can't decompose is a sign you don't understand it yet — flag it as a spike.

Step 4 — Size each subtask and sum

Give each subtask a T-shirt size with a rough hands-on range (these are illustrative — calibrate to the team and stack):

SizeRough rangeLooks like
S< ~0.5 daylocalized edit, pattern already exists in the repo
M~0.5–2 daysnew code across a couple of files, clear approach
L~2–5 daysnew seam or interface, touches several modules
XL> ~1 weekunknown approach, cross-cutting, or needs a spike first — decompose further

An XL is a smell: split it until the pieces are L or smaller, or call it a spike whose only deliverable is a smaller estimate. Sum the subtask ranges into a total range (low to high), not a single number.

WARNING

Do not just add the optimistic ends. Integration, review, and the inevitable "while I was in there" overhead are real — fold them in as their own line or a percentage, and let the high end of the range carry the unknowns rather than burying them.

Step 5 — Surface risks, dependencies, and assumptions

The estimate is only as good as what could blow it up. List, specifically:

  • Risks / unknowns that would inflate the number — undocumented behavior, a flaky area, a third-party API you haven't read the docs for, a refactor that might cascade. For each, note roughly how much it could add.
  • Dependencies / sequencing — what must land first, what's blocked on another team, what can run in parallel.
  • Assumptions — every "I'm assuming X" you relied on to size it (env exists, no data migration, the happy path only). If an assumption is wrong, the estimate changes — that's the whole point of writing them down.

Report

Deliver the estimate as your message — it is the whole deliverable.

## Effort estimate — <task>
 
**Scope:** <one sentence>
**Out of scope:** <the boundary>
 
| # | Subtask | Size | Range |
| - | ------- | ---- | ----- |
| 1 | Define provider config + types | S | < 0.5d |
| 2 | Add SAML assertion parser | L | 2–4d |
| 3 | Wire into the auth middleware | M | 1–2d |
| 4 | Characterization tests for the login path | M | 1–2d |
 
**Total range:** ~4.5–8.5 days (incl. review + integration)
 
**Top risks:** <each with how much it could add — e.g. "no tests on auth path: +1–2d if parsing breaks something">
**Dependencies / sequencing:** <what blocks what>
**Assumptions:** <the list — if any is wrong, the estimate moves>

End with the recommended first slice: the smallest subtask that retires the biggest unknown (usually a spike or the riskiest interface). Shipping it first tightens the whole range — call out which assumptions it will confirm or kill. Remind the reader the total is a range under these assumptions, not a date.

Frequently asked questions

Why a range instead of a single number?
Because the unknowns dominate. A point estimate hides the variance that actually decides whether the task slips. The range is the honest signal; the midpoint is just the middle of it.
Does this command write any code or plan files?
No. It is read-only — Read, Grep, and Glob only. The estimate is delivered as your message. Pair it with /breakdown-task or /plan-feature when you're ready to execute.